if(is_front_page()) {?> } else {?> } ?>
class="inner" } ?>>PROJECTS IN PROGRESS / COMPLETED.
ITEM NO. | CLIENT | PROJECT |
---|---|---|
2.1.1 | Proman Methanol 5000 | Fabrication & installation of approximately 800 tons of alloy steel piping (P11 & P91) |
2.1.2 | Petrotrin | #8CDU Test & Inspection |
2.1.3 | British Gas | HIPS Skid Package for the Dolphin Deep Project |
2.1.4 | Arawak Cement Company Ltd. Barbados | Ducting System |
2.1.5 | Government of Trinidad & Tobago | Installation of a roof canopy for Parliament building. |
2.1.6 | WASA | San Fernando Wastewater Treatment Plant. |
2.1.7 | NGC | Fabrication of vent stacks for the Cross Island Pipeline project ( CIPP ) |
2.1.8 | Bechtel International Incorporated | Fabrication of process piping for Atlantic LNG Trains 2 and 3 |
2.1.9 | Bechtel International incorporated | Installation of insulation in Joint Venture with Insulations Inc. for Atlantic LNG Trains 2 & 3 |
2.1.10 | Lurgi Caribbean Limited | Fabrication and installation of approximately 1800 tons of carbon steel piping for the Atlas Methanol project. |
2.1.11 | Guyana Water incorporated – Guyana | La Bonne international Water Project Lot II |
2.1.12 | RGM / PW Partnership | Supply, Fabrication And Erection Of Grand Stand For Manny Ramjohn Stadium – Marabella |
2.1.13 | WASA | Freeport Water Treatment Plant |
2.1.14 | TIDCO | Teteron Sewage Treatment Plant |
2.1.15 | Cliffs & Associates | Fabrication And Erection Of 2000 Mt Day Bin (at DR1 Plant) |
2.1.16 | Caribbean Ispat Limited | Installation Of Material Handling System (at DR3) |
2.1.17 | Cliffs And Associate | Total Mechanical Package Piping, Structural Steel And Equipment Installation (at DR1) |
2.1.18 | Fyzabad Community Centre | Refurbishment |
2.1.19 | U.W.I. Multi Purpose Hall | Fabrication & Erection |
2.1.20 | T&TEC Warehouse | Fabrication & Erection |
2.1.21 | Atlas Methanol | 1300 tonnes of carbon steel piping – Fabrication, Installation and Testing |
2.1.22 | Phoenix Park Gas Processors Limited- | Fabrication of three (3) Skids Above Ground Piping – 240 Tonnes. Under Ground Piping – 40 Tonnes. |
2.1.23 | Proman AG Trinidad Limited M5000 Project. | 640 Tonnes of P91 and P11 Piping Fabrication, Installation and testing. |
2.1.24 | Bechtel International INC. | 75 Tonnes of Stainless Steel Piping- Fabrication. |
FMCL Trinidad Ammonia Plant. Mechanical Work Corridor.
FMCL Trinidad Ammonia Plant. OSBL Mechanical Works.
KPAC/FMCL/PCN Leasing – Common Load-out Facilities.
Supply labour, equipment and materials to construct offsites interconnecting piperacks and tempered water facilities.
Complete installation coupled with all piping works.
Provide installation and consumable materials, labour, supervision, tools, construction equipment, rigging, services, scaffolding, temporary supplies and facilities, transportation, receiving, handling and warehousing/storage of each and every other item of expense necessary to complete the supply, fabrication, pre-assembly, testing transport to site of all components, field handling, field assembly/erection, and testing for the mechanical and piping work of the GCX revamp for Package ‘C’ at the Petrotrin Refinery located in Pointe-a-Pierre.
Shop Fabrication of carbon steel, alloy and stainless steel pipe spools for use on the Petrotrin Refinery upgrade project and covers the receipt, handling, inspection, storage and control of free issue piping materials and the fabrication, testing, inspection, stress relieving, radiography, sandblasting and painting of spool pieces and pipe supports for Unit #75.
Installation of all the rotating equipment for Ispat’s DR-3 Mega-Mod Project at Point Lisas through Lockwood Greene Zachary (USA) comprising of massive installation process and seal gas Roots compressors, gear boxes and generators, water treatment system equipment, chemical inhibition system and reformed gas compressors which are under completion and commissioning stage.